The Transmission Company of Nigeria on Thursday announced the addition of 600 megawatts to the national grid.
The Managing Director and Chief Executive Officer of TCN, Sule Abdulaziz, stated this at the official commissioning of the Ihovbor/Benin and Ihovbor/Ajaokuta 330kV Turn-In-Turn-Out Transmission Line Project here in Edo State.
Abdulaziz said the project marked another milestone in the collective journey to strengthen the nation’s transmission network, enabling the country to evacuate more bulk electricity from the Ihovbor transmission substation to distribution load centers nationwide.
Also Read:
- Kogi, Niger Residents to Experience Blackout as TCN Carries Out Maintenance on Okene, Tegina…
- No Improvement in Electricity Generated, Wheeled by TCN since 2015 - DisCos
- TCN Announces Six-Hour Power Outage in Ogun Communities for Transformer Maintenance
- Testing the Limits of Estate Associations' Powers: Megawatts Nig Ltd v. Gbagada Phase 2…
He added: “This project involves the strategic linking of the existing Benin/Ajaokuta 330kV transmission line to the Ihovbor Transmission Substation, creating two new transmission routes with a total length of 14 kilometres.
“With the completion of this strategic project, we have increased the operational flexibility of the transmission network and strengthened the resilience of power delivery within the Benin corridor through this connection to the power plant.
“The importance of this project cannot be overstated. It grants TCN the ability to more efficiently evacuate power generated by the Azura Power Plant and the Niger Delta Power Holding Company plant.
“This has equally helped in alleviating transmission bottlenecks, enhanced system reliability, while allowing the distribution companies access to more bulk electricity for their customers nationwide. With this, we have added 600 megawatts to the national grid.”